Repairs are planned to rehabilitate the Waterford River Bridge at Blackhead Road, with construction scheduled to begin on Mon. May 8 and be completed by the end of August.
The bridge will remain open to traffic during construction with lane reductions required. Work will take place from Monday to Friday, from 7 a.m. to 7 p.m., slowdowns and traffic disruptions are expected.
The contractor for the project is Pyramid Construction Limited. The project involves general concrete rehabilitation works, expansion joint replacements, guide rail repairs, waterproofing and paving the bridge deck.