Friday, August 25, 2017 - 3:40 PM

Sanitary Sewer Lining (Goulds)

Location: 
Goulds - Various Streets
Start Date: 
Monday, August 28, 2017 - 7:00am to Thursday, November 30, 2017 - 6:00pm

Contractor will be conducting sanitary sewer rehabilitation work on various streets in Goulds.  Traffic interruptions and delays may be experienced during this project; however, kept to a minimum and two-way traffic will be maintained.  Flag persons will be used to direct traffic when necessary.
  
Sewer service interruptions will be experienced on occasion and residents will not be permitted to flush toilets or use water fixtures/appliances (such as dishwashers, clothes washers, running water down sinks, etc.) during CIPP liner installation operations.  The flushing of toilets or use of water fixtures/appliances during liner installation will cause a backup of water/sewer and flooding of your property, as the sewer service line from your property will be blocked by the liner at the sewer main.  In addition, the introduction of water into the sewer prior to completion of the liner installation process may damage the liner.  Once the liner installation process is complete and the sewer service line re-opened to the sewer main (entire process may take up to 12 hours), you will be notified by the Contractor that the use of water and sewer fixtures is again permitted.  The City of St. John's apologizes for any inconvenience. If you require further information, please visit engagestjohns.ca or contact Access St. John's at 311 or 754-CITY (2489).
  Sanitary Sewer Lining will be completed on the following streets:
  BOLAND STREET (Civic #12 to Keith Drive)
  CLEARVIEW STREET (Civic #17 to Ridgemount Street)
  GULLAGE SRTEET (Civic #11 to Keith Drive)
  KEITH DRIVE (Ridgemount Street to Main Road)
  MAIN ROAD (Doyle’s Road to McGrath Place)
  MEADOWBROOK DRIVE (Main Road to Bridge)
  MEADOWBROOK PARK PLACE
  MEADOWBROOK PARK ROAD
  NORTH DRIVE
  RIDGEMOUNT STREET (Civic #10 to Keith Drive)
  WALSH PLACE